Numerous failures in the management of a sewage pumping station operated by the company led to sewage created by two villages emptying into two brooks leading to the River Evenlode, a tributary of the River Thames, for up to 24 hours. Judge Ross found Thames Water had polluted Idbury and Littlestock brooks at Milton-under-Wychwood, near Chipping Norton, on 8th and 9th August 2015. Environment Agency officers were quickly on site, discovering the entire local population of almost 150 bullhead fish had been killed by the toxic waste along a 50-metre stretch of water.

A member of the public reported dead fish in Idbury brook to the Environment Agency. A backlog of raw sewage was forced into the water from a sewer pipe that couldn’t hold it. Sewage also escaped from a manhole and onto a residential front garden.

Thames Water were found to have disregarded more than 800 high-priority alarms needing attention within four hours in the six weeks before the incident. Another 300 alarms were not properly investigated, all of which would have pointed out failures with the pumping station. One alarm was deliberately deactivated during a night shift. Investigations by the Environment Agency revealed Thames Water was aware the pumping station failed several times in the 12 months up to and including the incident in August 2015.

Robert Davis, who led the investigation for the Environment Agency, said, “This incident was foreseeable and avoidable. Thames Water didn’t recognise the increased risk to the environment, ignoring or failing to respond adequately to more than 1,000 alarms. These streams are normally a haven for kingfishers, grey herons, brown trout and other fish and invertebrates. Sewage poured into the water for 24 hours, having a terrible impact, killing fish and other water life. We hope this prosecution sends a loud and clear message that the Environment Agency will not accept poor operation, management and maintenance of sewage pumping stations. Where we have evidence of offending and serious pollution incidents like here, we will take appropriate action to bring polluters to justice.”

Judge Ross said Thames Water was ‘reckless’ by taking an unacceptable level of risk with the environment. It allowed the sewage pumping station to operate with no automatically available standby pump for around 10 months in the year prior to the pollution. Environment Agency officers discovered other information and data highlighting repeated problems with the pumping station in the year before the pollution, which Thames Water failed to report to the Environment Agency.

Judge Ross also ordered Thames Water to pay full costs of £79,991.57. The company pleaded guilty at an earlier hearing to two charges of breaching environmental law.

Assurity Consulting are leading experts in workplace health, safety and environmental compliance. If you would like to find out more about the services we offer, and how we can help you, please contact us on tel. +44 (0)1403 269375 or email us